Monday, 2 November 2009
ATJ Building
Posted using ShareThis
Sunday, 9 August 2009
Brickwork inc DPC’s and Cavity trays
First the existing brickwork was cut out allow the new internal skin to join the existing internal brickwork, this maintains the cavity and stops the cavity being bridged which cause damp problems. Wall starters were then fixed to the existing brickwork. We prefer to use “Wall Starters” rather than physically teething into the brickwork because the brick size, the gauging on the existing brickwork is not consistent and if there is any settlement the toothed bricks are likely to break which would be a costly repair. Where as if settlement occurs and wall starter are used there is no damage as the straight joint where the 2 walls meet should be filled with a flexible water proof sealant. Anyway………………..
The openings and bond were set out and profiles installed.
The next job was install the damp proof course (DPC) and cavity tray. The damp proof membrane (DPM) / Radon Barrier from the slab is brought through to the outer skin of brickwork, a block is then laid on the inside skin. Next a 450mm wide DPC is laid on the brickwork lapping up to the next block course creating a tray, another block is laid on the inside skin. Next a course of bricks is laid over the DPC and a weep outlet placed in a joint every 1.5m
The brickwork then proceeded, building the outer skin 1st then “backing it up” with the blockwork installing the cavity insulation as work progressed. The lintels were bedded on and another cavity tray install exactly the same as on the DPC. The wall plates were bedded on the blockwork at the correct height and the brickwork to the gables continued building in the 1st floor window profiles and install the lintels. The brickwork to the Gables could not to finished until the roof is cut, however the cavity closers were install the the openings, it is good practice to keep the brickwork, blockwork and cavity dry.
Terry J
Sunday, 19 July 2009
Extension & Loft Conversion Foundations & Over site.
This is a recently completed Home Extension and loft conversion. The Bungalow was extended 2.3m out the back, 3.3m to the side and a 1st floor constructed to create a loft conversion.
The 1st part to this project was the Groundwork, Foundation and Over site. The fence was taken and conservatory demolished. Next the Ground was reduced to approximately 450mm below finish floor level (FFL) to allow for hardcore, insulation, concrete and screed.
Then the building was set out with lines and profiles, Foundations were dug and inspected by building control before concrete was poured. Next the Drainage under the over site was installed leaving tails out of the building to connect on to at a later date.
The Brickwork was then Built up to Damp Proof Course (DPC) bridging over the drains with lintels. 150mm of hardcore was laid and compacted followed by 25mm soft sand blinding, then 1200 gauge Damp Proof Membrane laid bridging the cavity to create a radon barrier. 100mm of insulation was cut and installed before building control inspected the over site. Once the over site was inspected the floor slab was concreted which completed the 1st stage of this project the site strip, Foundations, Brickwork up to DPC and Over site.
Terry J
Monday, 13 July 2009
Repairs to Impact Dammaged Property
Wednesday, 1 July 2009
Garden Design & Construction inc Blockpaving
We have recently completed a garden design and construction project as part of a much larger home renovation including side and rear home extension, loft conversion, and garage. There are several aspects to this project which include:-
Feature fire place and decorative brickwork with a segmental arch, shortened breast and chimney stack. The Fire place is capped with Marshall slabs to create a mantel peace.
Block Paving with a charcoal boarder, brindle infill with a herring bone pattern, the paving falls away from the house into an acco channel direct to a new soak away.
Feather edge / close board fencing behind the fire place to separate it from the parking area.
Terry J